New procurement of Kvarnberget phase

We procure a contractor for building of the Kvarnberget phase of the West Link.

The offer was sent on December 7th and the closing date is May 18th, 2018.

The procurement of the Kvarnberget phase was canceled earlier this year due to lack of competition. There was only one bid and the tender amount was higher than the budgeted calculation. To open up for more bidders, this procurement will be without prequalification, which was used previously.

"We estimate that we have a contractor in place at the beginning of June 2018," says Edina Smlatic, project manager Kvarnberget.

Because of the cancelled previous procurement, the start of the contract will be delayed. This means that the reinforcement work in the Göta Tunnel will not be part of the Kvarnberget phase. Instead it will be an addition to the contract for the Centralen phase.