Double tracks

Jakobshyttan–Degerön

We’re planning to build double tracks on the Jakobshyttan–Degerön route. 

The route is approximately 13 kilometers long. 5 km of new track running alongside the existing one, and 6 km of double tracks in new terrain.

We will also build a 1 km station with a passing loop.

What´s happening now?

The railway plan has acquired legal force. Construction is scheduled to start in 2021.

  • Current procurement: Design and Build Contract.
  • Estimated cost: EUR 71 million.
  • Tender day: End of February 2021.

More facts on Double tracks between Hallsberg and Degerön, including map and schedule.