Information for suppliers

On Thursday 11 April The Swedish Transport Administration (Trafikverket) arrange the Suppliers Day in Stockholm, to present future major business opportunities in 2019-2022.

We have many new road and rail assignments across the country. One of these projects is Goods line Avesta Krylbo–Dalslund, double track.

Goods line Avesta Krylbo–Dalslund, double track

Measures to increase the capacity of the goods line between Avesta Krylbo and Dalslund, about 5 km. The measures will also have a positive effect on the Dala line.

Railway plan including location investigation to find the best options for increasing the capacity of the freight line between Avesta Krylbo and Dalslund (about 5 km), including Krylbo depot.

Procurement information: Planning Construction documents. Sending out tender documents autumn 2019.
Cost: SEK 10 - 20 million

Procurement information: Construction documents. Sending out tender documents spring 2021.
Cost: SEK 5 - 10 million

Procurement information: Production. Sending out tender documents Spring 2022.
Cost: SEK 100-300 million

Contact: Anders Danielsson
+46 72-142 22 07

The Swedish Transport Administration's Suppliers Day 11 april 2019