What: Double tracks on the West Coast line through Varberg. New station. New freight yard.
New double tracks: 7.5 km
Open concrete trough: 900 m
Concrete tunnel: 300 m
Rock tunnel: 2.8 km
Why: To create better opportunities for commuting and to be able to transfer freight transportation to the railway.
Schedule: Planning and design 2015-2018, construction phase 2019-2024 approx.
Cost: SEK 3.99 billion (2009 price level)